If you are planning a high-rise residential development in England, the way it is designed, assessed against the Building Regulations and delivered has changed significantly.
Under the Higher-Risk Building regime, much of the design work that was traditionally developed during construction now needs to be resolved before work starts on site. For clients, this changes how projects need to be planned, resourced and programmed.
What is a Higher-Risk Building?
During design and construction, a building is generally classed as a Higher-Risk Building (HRB) if it:
- is at least 18 metres high or has at least seven storeys, and
- contains at least two residential units.
Hospitals and care homes that meet the same height threshold are also included.
The three gateways
- Gateway 1 (planning): For relevant developments, a Fire Statement must accompany the planning application. It sets out the fire safety considerations that have informed the proposals. It is not a Building Regulations compliance assessment.
- Gateway 2 (before construction): An application for building control approval must be submitted to the Building Safety Regulator (BSR), which assesses it against the Building Regulations. Building work covered by the regime cannot start until approval has been granted. The statutory determination period is 12 weeks for new HRBs and 8 weeks for work to existing HRBs, although determination can take longer in practice.
- Gateway 3 (completion): The client applies to the BSR for a completion certificate, providing prescribed information about the completed work. The statutory determination period is 8 weeks. The building cannot be occupied until the completion certificate has been issued, subject to any arrangements for partial completion. It must also be registered with the BSR before occupation.
Throughout the project, the building’s golden thread information must be maintained and handed over as required.
The old way of working no longer applies
Specialist design contractors have traditionally been appointed at RIBA Stage 5, sometimes after construction had started. These contractors are responsible for Contractor’s Designed Portions (CDPs), such as façades, lifts and building services packages. Design details and coordination were then developed as work progressed on site.
For HRB projects, that approach can create significant challenges. The Gateway 2 application needs to demonstrate how the proposed work will meet the relevant Building Regulations requirements before the work begins. This means specialist input may need to be secured earlier, often during RIBA Stage 4.
Some CDP information can still be developed after Gateway 2 approval, but this needs careful planning. The application should explain:
- how compliance will be demonstrated,
- how the outstanding design information will be provided, and
- how that information will be managed and integrated into the approved design.
The BSR may grant approval with requirements in certain circumstances, allowing specified information to be provided later. This is not a substitute for developing the design to the level needed for the application, and the BSR’s decision cannot be assumed in advance. We have experience in preparing strategies for applications where approval with requirements may be appropriate.
Where suitable, a Gateway 2 application can also be submitted in stages, with each stage approved before the related work starts. This route needs to be planned carefully from the outset.
Late design development also has consequences after approval. Changes to the approved design must be managed through a change control process. Some changes must be notified to the BSR, and major changes require BSR approval before the relevant work is carried out. This can affect the construction programme.
The benefits of earlier coordination
Front-loading the design process is not just a response to regulation. It can also support better delivery of complex buildings.
Issues that might previously have emerged on site can be identified and addressed earlier in the design process. This can support a more predictable construction programme and provide a stronger basis for coordination.
Clients need to allow sufficient time in their programmes for design development and the Gateway 2 application. If we are involved early enough, we can help clients consider the programme and the information needed at each stage.

People and responsibilities before deliverables
Clients have duties under the Building Regulations. These include making suitable arrangements for planning, managing and monitoring building work, and appointing the required dutyholders.
The dutyholders include the Principal Designer (PD) and Principal Contractor (PC) under the Building Regulations, where the appointment requirements apply. These roles are separate from the CDM 2015 roles of the same name, although the same organisation can be appointed to both.
The PD and PC have distinct duties in relation to design work and building work respectively. These include coordinating matters relating to compliance with the Building Regulations.
The client should appoint the required dutyholders in writing and at the appropriate time. The client remains responsible for assessing the competence of those it appoints, and a suitably experienced PD can support this process. We have developed assessment criteria informed by the competence requirements in Part 2A of the Building Regulations 2010 (as amended).
Once the team is in place, roles, design responsibilities and tasks should be clearly defined. We can assist clients in establishing and documenting the relevant appointments.
A well-structured application
A Gateway 2 application requires more detailed information than a traditional building control application. Sufficient time needs to be allowed to prepare, coordinate and compile the information for submission.
The application includes mandatory documents, such as:
- a Building Regulations Compliance Statement
- a Fire and Emergency File
- a Construction Control Plan
- a Change Control Plan
- a Mandatory Occurrence Reporting Plan
- a competence declaration
- a partial completion strategy, where relevant.
Depending on our appointment, we can prepare some of these documents or coordinate their preparation with the relevant dutyholders. Several of them need input from the Principal Contractor. We can also help the client understand the declarations required as part of the application.
Where appointed as Principal Designer under the Building Regulations, we plan, manage and monitor the design work and coordinate matters relating to it, in line with our agreed scope. Our processes, documentation frameworks and practical experience support the preparation of structured Gateway 2 submissions.
At ECE Architecture, we have worked on applications for new HRBs and for building work to existing HRBs. This experience informs our understanding of the information the BSR may require when assessing an application.
Plan for it now
In our experience, projects progress more smoothly where Gateway 2 is treated as a design discipline from the outset. This means building the application into the programme and aligning the design team, information requirements and decision-making early. It should not be treated as a regulatory box to tick at the end of RIBA Stage 4.
If you are in the early stages of an HRB project, we can help you develop a project strategy that takes account of the design and application requirements.